“Rehabilitation of the Breakwater of Port Varna – phase II” – 2006-2009

  • Repair of existing blocks;
  • Making of reinforced concrete pavement with ribs;
  • Building of an underwater berm of stones- 500-1500 kg. up to level – 7; – 46 000 cubic metres;3
  • Mounting of wave breaking concrete boxes of single weight 35.5 tonnes – 288 pcs.
  • Filling up of the concrete boxes with stones of weight of 500kg.;
  • Building of a berm of stones of 100-500kg. at the inner side of the breakwater- 3050 cubic metres;3
  • Building of a monolithic breakwater – casting of 87 square metres;2
  • Mounting of hexapods of single weight 2 tonnes – 6722 pcs.