“Preparation and moving of Dock 2 and preparation and mounting of new dock in the region of Shipyard “Odessos”- Varna 2009-2010

  • Dredging according to the assigned depth, executed with 10t floating crane, flat barge with chain excavator, split barge 1000 m3, dredging pump, temporary depot and a commercial diving team
  • Taken out 12 dead anchors of Dock 2 with 100 t floating crane, and precise positioning of the new anchors as well as anchoring of the Dock.
  • Mounting of 20 dead anchors for the installation the new Dock.